Projects / Roads & expressways
HCMC–Thủ Dầu Một–Chơn Thành ExpresswayCao tốc TP.HCM – Thủ Dầu Một – Chơn Thành
The industrial spine through Bình Dương’s factory belt. Under construction since February 2025; no completion date in VIRO’s evidence.
Readiness ladder · Thang sẵn sàng
Why this stage
The Prime Minister ordered construction to start on 1 February 2025; by July 2026 compensation and site clearance were still being completed.
Reported 10 Jul 2026 · Báo Đầu tư
Next rung — Partly operational: Some sections or functions in use; route-wide or full operation not established.
Observed stage
In plan
Approved
Investor / contractor selected
Under construction
Partly operational
Operational
Usable for business
Site / institution
Milestones · Mốc kế hoạch và thực tế
Planned against achieved
| Milestone | Planned / target | Achieved | Status | Source |
|---|---|---|---|---|
| Construction start ordered | — | 1 Feb 2025 | Achieved | Báo Đầu tư |
| Clean-site handover | Q3 2026 | — | Unknown | Báo Đầu tư |
| Completion | — | — | Unknown | Báo Đầu tư |
Evidence · Bằng chứng
What the record shows
- Reported10 Jul 2026A national key transport project. The Prime Minister ordered construction to start on 1 February 2025 and required early completion. Land recovery covers more than 327.2 ha and affects 1,613 households, individuals and organisations, with VND 8,283.2 billion budgeted for clearance.
- Reported10 Jul 2026HCMC reported that some cases still lacked an approved compensation plan, had not taken compensation or had not handed over land, which it called a risk to the schedule, and made clearance an urgent task for Q3 2026. The report gives no completion date.
Unknown · Chưa rõ
- Share of site handed over.
- Section-by-section opening dates.
- Completion and operation dates.
- Total length and contract form.
VIRO analysis
It would give the northern industry pole a dedicated expressway to the city and the ring roads.
Sources · Nguồn
- Deadline set for clean-site handover on HCMC–Thủ Dầu Một–Chơn Thành expressway — Báo Đầu tư, 10 Jul 2026
Next project: LNG Long Sơn power project