LNG Long Sơn power projectDự án điện khí LNG Long Sơn

A 1,500 MW LNG plant on the coast. Investment policy approved in March 2026; no investor selected in VIRO’s evidence, and commercial operation is targeted for June 2031.

2/7 · Approved · Phê duyệt chủ trươngLast observed 31 Oct 20261 sources
Readiness ladder · Thang sẵn sàng
Why this stage

Decision 1702/QĐ-UBND of 24 March 2026 approved the investment policy, with the investor to be chosen by competitive tender.

Fact  24 Mar 2026 · Báo Đấu thầu

Next rung — Investor / contractor selected: A delivery party is selected; construction not yet observed.

Schematic map of Southern Vietnam infrastructure projects by readiness stageApproximate positions of tracked projects in and around Ho Chi Minh City, coloured by observed delivery stage. Not for navigation.ĐỒNG NAITÂY NINHĐỒNG THÁPHỒ CHÍ MINH CITYEast SeaThủ Thiêm–Long Thành Railway — In planHCMC Ring Road 3 — Under constructionHCMC Ring Road 4 — Under constructionMetro Line 2 (Bến Thành–Tham Lương) — Under constructionHCMC–Mộc Bài Expressway — Under constructionHCMC–Thủ Dầu Một–Chơn Thành Expressway — Under constructionBiên Hòa–Vũng Tàu Expressway — Partly operationalBến Lức–Long Thành Expressway — OperationalHCMC–Long Thành–Dầu Giây Expressway (widening) — OperationalMetro Line 1 (Bến Thành–Suối Tiên) — OperationalHCMC coreThủ ĐứcBiên HòaThủ Dầu MộtBàu BàngPhú MỹVũng TàuBến LứcHiệp PhướcCủ ChiLong Thành International Airport (phase 1) — Under constructionCái Mép–Thị Vải deep-water port cluster — Usable for businessCần Giờ International Transshipment Port — Investor / contractor selectedNhơn Trạch 3 & 4 LNG power plants — OperationalHCMC Free Trade Zone (Cái Mép Hạ) — ApprovedVietnam International Financial Centre (HCMC) — OperationalDirect power purchase (DPPA) rules — ApprovedLNG Long Sơn power project — Approved
Observed stage
In plan
Approved
Investor / contractor selected
Under construction
Partly operational
Operational
Usable for business
Site / institution
Schematic, approximate geometry for orientation — not navigation or project alignments. Pole circles follow the structure of the HCMC master plan; they are not official boundaries. Observation run 31 Oct 2026.
Milestones · Mốc kế hoạch và thực tế

Planned against achieved

MilestonePlanned / targetAchievedStatusSource
Investment policy approved—24 Mar 2026AchievedBáo Đấu thầu
Investor selectedJun 2026—UnknownBáo Đấu thầu
Commercial operationJun 2031—PendingBáo Đấu thầu
Evidence · Bằng chứng

What the record shows

  • Target
    3 Apr 2026
    The planned sequence was to finish investor selection by June 2026, complete the feasibility study and negotiate the power price and PPA from mid-2026 to mid-2027, arrange finance, clear the site and select an EPC contractor in 2027–2028, and build in 2028–2031. VIRO found no report that an investor has been selected.
  • Reported
    3 Apr 2026
    Reported obstacles for LNG power generally: the electricity-price mechanism and minimum contracted output in the PPA, raising debt as international lenders grow cautious on fossil projects, and LNG price and exchange-rate volatility. Of 15 LNG plants planned to operate in 2025–2030, only Nhơn Trạch 3 and 4 were complete at the time of reporting.
  • Fact
    24 Mar 2026
    Decision 1702/QĐ-UBND of 24 March 2026 approved the investment policy: about 1,500 MW, preliminary investment of VND 39,867 billion (about US$1.6 billion) at 20% equity and 80% debt, a 50-year operating period and a target of commercial operation in June 2031.
  • Fact
    24 Mar 2026
    The 42.56 ha site includes 12 ha of protective forest land. The investment-policy decision states that if the project cannot meet the conditions for converting forest land, the competent authority may consider terminating it.
Unknown · Chưa rõ
  • Whether an investor has been selected.
  • Power purchase agreement and electricity price.
  • Forest-land conversion.
  • Construction start.
VIRO analysis

The coastal energy corridor in the draft plan depends on projects like this moving from an approved policy to a signed power contract and a selected investor.

Serves
Pole 5 · Southern port–FTZ–energy pole
Corridor · Southern coastal corridor
Poles & corridors →
Sources · Nguồn

Next project: Long Thành International Airport (phase 1)