Thủ Thiêm–Long Thành RailwayĐường sắt Thủ Thiêm – Long Thành

The planned rail link from the new financial district to the airport. Still in appraisal when last reported; it will not be ready when the airport opens.

1/7 · In plan · Trong quy hoạchLast observed 31 Oct 20262 sources
Readiness ladder · Thang sẵn sàng
Why this stage

In January 2026 the Government issued conclusions on accelerating rail links, including Thủ Thiêm–Long Thành.

Fact  4 Jan 2026 · Government News

Next rung — Approved: Investment policy, legal instrument or establishment decision issued.

Schematic map of Southern Vietnam infrastructure projects by readiness stageApproximate positions of tracked projects in and around Ho Chi Minh City, coloured by observed delivery stage. Not for navigation.ĐỒNG NAITÂY NINHĐỒNG THÁPHỒ CHÍ MINH CITYEast SeaThủ Thiêm–Long Thành Railway — In planHCMC Ring Road 3 — Under constructionHCMC Ring Road 4 — Under constructionMetro Line 2 (Bến Thành–Tham Lương) — Under constructionHCMC–Mộc Bài Expressway — Under constructionHCMC–Thủ Dầu Một–Chơn Thành Expressway — Under constructionBiên Hòa–Vũng Tàu Expressway — Partly operationalBến Lức–Long Thành Expressway — OperationalHCMC–Long Thành–Dầu Giây Expressway (widening) — OperationalMetro Line 1 (Bến Thành–Suối Tiên) — OperationalHCMC coreThủ ĐứcBiên HòaThủ Dầu MộtBàu BàngPhú MỹVũng TàuBến LứcHiệp PhướcCủ ChiLong Thành International Airport (phase 1) — Under constructionCái Mép–Thị Vải deep-water port cluster — Usable for businessCần Giờ International Transshipment Port — Investor / contractor selectedNhơn Trạch 3 & 4 LNG power plants — OperationalHCMC Free Trade Zone (Cái Mép Hạ) — ApprovedVietnam International Financial Centre (HCMC) — OperationalDirect power purchase (DPPA) rules — ApprovedLNG Long Sơn power project — Approved
Observed stage
In plan
Approved
Investor / contractor selected
Under construction
Partly operational
Operational
Usable for business
Site / institution
Schematic, approximate geometry for orientation — not navigation or project alignments. Pole circles follow the structure of the HCMC master plan; they are not official boundaries. Observation run 31 Oct 2026.
Milestones · Mốc kế hoạch và thực tế

Planned against achieved

MilestonePlanned / targetAchievedStatusSource
Feasibility-study appraisal council set up—28 Jul 2026AchievedThị trường Tài chính Tiền tệ
Construction start2 Sep 2026—UnknownThị trường Tài chính Tiền tệ
Completion and operation2030—PendingThị trường Tài chính Tiền tệ
Evidence · Bằng chứng

What the record shows

  • Target
    28 Jul 2026
    HCMC set up the feasibility-study appraisal council on 28 July 2026, which appraises the study under the PPP law. At that point the city targeted a groundbreaking around 2 September 2026 and operation in 2030. VIRO found no report that the groundbreaking took place.
  • Reported
    28 Jul 2026
    The line is about 47.7 km through HCMC and Đồng Nai, designed with 18 stations (2 underground, 16 elevated); HCMC proposed building 14 of them first. Preliminary investment is about VND 175 trillion and more than 144 ha must be recovered, with compensation split into a separate component project funded by HCMC and Đồng Nai.
  • Fact
    4 Jan 2026
    Government conclusions in January 2026 directed acceleration of rail links to Long Thành.
Unknown · Chưa rõ
  • Exact alignment.
  • Investment decision and timeline.
  • Service start.
VIRO analysis

A rail link would make Long Thành part of the city rather than a remote airport.