Projects / Roads & expressways
HCMC Ring Road 4Đường Vành đai 4 TP.HCM
The outer orbital through Bình Dương, Đồng Nai and the former Long An. The first PPP works started in October — in Tây Ninh, not in the HCMC core segment.
Readiness ladder · Thang sẵn sàng
Why this stage
On 15 October 2026 Tây Ninh launched construction of PPP components 2-4 and 2-5 (nearly 78 km, investor Sơn Hải Group).
Reported 15 Oct 2026 · Dân Trí (DTiNews)
Next rung — Partly operational: Some sections or functions in use; route-wide or full operation not established.
Observed stage
In plan
Approved
Investor / contractor selected
Under construction
Partly operational
Operational
Usable for business
Site / institution
Milestones · Mốc kế hoạch và thực tế
Planned against achieved
| Milestone | Planned / target | Achieved | Status | Source |
|---|---|---|---|---|
| HCMC core-segment groundbreaking | 2 Sep 2026 | — | Unknown | Vietnam News Agency |
| Tây Ninh PPP components 2-4, 2-5 start | — | 15 Oct 2026 | Achieved | Dân Trí (DTiNews) |
| Tây Ninh components complete | — | — | Unknown | Dân Trí (DTiNews) |
Evidence · Bằng chứng
What the record shows
- Reported15 Oct 2026Tây Ninh held a launch ceremony on 15 October 2026 for PPP components 2-4 and 2-5, from Thầy Cai canal to Hiệp Phước port: nearly 78 km, over VND 43 trillion (about US$1.63 billion), investor Sơn Hải Group. The Tây Ninh section is to open with four lanes at a 100 km/h design speed, passing 15 communes. The report gives no completion date.
- Reported15 Oct 2026The whole Ring Road 4 route is about 159 km.
- Fact12 Aug 2026Three PPP components (2-2, 2-4, 2-5) were in investor selection on 12 August 2026.
- Fact12 Aug 2026Two component feasibility studies (2-1, 2-3) remained under appraisal.
- Reported31 Jul 2026Selected public-investment enabling works were reported to have started; this does not establish construction of the core expressway.
Unknown · Chưa rõ
- Whether the HCMC core-segment groundbreaking took place.
- Investor for Đồng Nai component 2-2.
VIRO analysis
Ring Road 4 is the spine for the next generation of industrial land in northern Bình Dương and around Phú Mỹ.
Serves
Pole 2 · Eastern innovation pole
Pole 4 · Northern industry–logistics pole
Pole 5 · Southern port–FTZ–energy pole
Corridor · North–South corridor
Corridor · East–West corridor
Poles & corridors →Sources · Nguồn
- Tây Ninh launches VND 43 trillion HCM City Ring Road 4 project — Dân Trí (DTiNews), 15 Oct 2026
- Southern expressway update, including Ring Roads 3 and 4 — Viet Nam Government News, 12 Aug 2026
- HCMC plans Ring Road 4 expressway package groundbreaking — Vietnam News Agency, 31 Jul 2026
Next project: Biên Hòa–Vũng Tàu Expressway