HCMC–Mộc Bài ExpresswayCao tốc TP.HCM – Mộc Bài
The expressway to the Cambodian border gate. Under construction since July 2026; completion expected in 2028.
Readiness ladder · Thang sẵn sàng
Why this stage
Work was reported active at the Provincial Road 8 and 15 interchanges in Củ Chi in early October 2026.
Reported 5 Oct 2026 · CafeF
Next rung — Partly operational: Some sections or functions in use; route-wide or full operation not established.
Observed stage
In plan
Approved
Investor / contractor selected
Under construction
Partly operational
Operational
Usable for business
Site / institution
Evidence · Bằng chứng
What the record shows
- Reported5 Oct 2026The expressway is about 51 km — 25 km in HCMC and 26 km in Tây Ninh — ending at National Highway 22 in Bến Cầu near the Mộc Bài international border gate, with four lanes and five interchanges and funding of nearly VND 23 trillion. Construction started in early July 2026 and the whole route is expected to be completed in 2028.
- Reported5 Oct 2026In Tây Ninh, land clearance was essentially complete in early October 2026 at 99.5%, with 11 of 2,274 cases not yet handed over. Clearance was still under way in some other areas. VIRO has no figure for the HCMC side.
Unknown · Chưa rõ
- Land-clearance progress on the HCMC section.
- Whether a toll or BOT structure applies.
VIRO analysis
It is the northern end of the North–South corridor and the main road link to Cambodia.
Serves
Pole 3 · Western urban–health–education pole
Pole 4 · Northern industry–logistics pole
Corridor · North–South corridor
Poles & corridors →Sources · Nguồn
- HCMC–Mộc Bài expressway construction intensifies — CafeF, 5 Oct 2026